Discussion about this post

User's avatar
Martin E's avatar

I’m retired now from NG transmission and this never was my patch, I think the closest I got was some protection equipment work at Iver maybe 25 ish years ago so the only insight I have is what’s been in the press and access to the published transmission system maps which for some reason omit North Hyde completely. In fact I’m really struggling to find any other omissions elsewhere.

I can’t believe the bollocks sprouted by the media and ‘experts’ about this incident although it’s only to be expected!

The total lack of fire separation barriers surprised me, after the massive supergrid transformer fire at either Rochdale or Padiham in Lancashire in the late 1980’s lots of barriers were installed together with increased height bund walls, & fire suppression systems. As far as the North Hyde site is concerned, In the footage and on Google earth, for the one that caught fire you can see rigid busbars from the transformer bushings crossing over the internal access road and around the relay rooms into the lower voltage compound. The western and immediately closest circuit to the one that caught fire looks to cross the road into the compound on a catenary strung from an overhead gantry, and the eastern, most right hand one with large separation from the other two is possibly terminated in a cable sealing end, destination unknown, it could be another DNO substation, or the far side of the North Hyde 66kV/22kV site.

The 275kV busbar sections would in normal circumstances be run split so you’d have two 275kV/66kV transformers effectively on one 275kV feeder, and the remaining 275kV transformer on the other feeder. The 66kV sub with at least two sections and possibly more would then, in normal circumstances, require a double circuit failure of the HV side to cause a total loss of supply (a double circuit feeder fault) At the far end of the 275kV feeders at Iver they’d be on separate busbar sections and so the likelihood of loss of both supplies is quite low but not impossible.

The windings of the transformer are enclosed in oil, circulated and cooled by external coolers (radiators) If there was a transformer fault it might be preceded by the detection of gas being produced within the oil as it decomposes. If this is gradual then in the first instance generate an alarm, normally resulting in a site visit and an oil sample being taken for lab analysis. A rapid production of gas by a failure resulting in an internal arc would result in lots of gas being produced, in those circumstances the transformer would be automatically disconnected from the HV (275kV) supply using a circuit breaker (a device that can break load and fault current) and then automatically disconnected from the LV (66kV) load using a disconnector (a device that isn’t intended to break load and fault current) Hopefully this occurs rapidly without disruption of the transformer tank and cooler bank. But a large overpressure would be relieved by burst discs and oil would end up hopefully within the oil containment bund.

So following the transformer failure, and assuming there is no collateral damage it would still leave the entire 66kV/22kV sub still serviceable, possibly with some loss of supply from bars fed by the failed transformer. At this point reconfiguration to maintain essential supply to Heathrow could be relatively easy.

But if a catastrophic failure of the transformer or cooler bank happened with oil spraying or misting onto live conductors it could ignite.

That’s a holding situation but as the fire progresses the closely sited transformer would at some point either trip on fault maybe with bushing contamination from the combustion products or with winding temperature, or when the extent of the incident became visible it would be manually switched out of service.

One thing to note is all circuits at 66kV and below leave via cable regardless

There are still 66kV networks around elsewhere, off the top of my head, in the North East (Hawthorn Pit, Hartmoor, Lackenby, West Bolton & Norton) and in South Yorkshire (Thurcroft, West Melton & Thorpe Marsh, plus a handful more). All were associated historically with coal mining

Plus the North East has quite a bit of 20kV (yes 20 not 22) lines such as in and around the Hexham area (there was even a new 275kV/20kV sub built on the cross Pennine west of Newcastle route from Stella West to Harker about 25 years ago, named Fourstones)

As an aside, on the previous Friday, the 14th March at 0851 three units near simultaneously tripped at Drax, one on its own and then five secs later two more 1887MW loss of generation. Virtually nothing said anywhere. No lightning activity. No press releases from NESO or Drax plc. Now it could be someone messing up preparing for testing and there is an internal enquiry ongoing but losing generation spread over at least two and possibly three busbar sections is very strange. The frequency dropped to 49.667Hz. Data is visible on elexon. I do have screen caps.

Expand full comment
Hills's avatar

I know very little about electricity supplies so this has been illuminating & fascinating to read. Thanks. The unfortunate facts about old kit not lasting for ever are well known.

The ever increasing demand on all the UK infrastructure & a plan to address this - water, land, roads, power, housing - is rarely acknowledged publicly. At least not in a mature rational discussion. I have so little confidence in those in power to enable this without media meltdown I end up & shrug my shoulders & hope someone skilled & competent who genuinely know what they are doing will sort it out. I wasn’t going in or out of Heathrow at the time - so I’m OK Jack.

I guess we have more of these sorts of catastrophic failures to come.

Expand full comment
37 more comments...

No posts